Pittsfield Roadwork Schedule For Week Of Sept. 10
Finish pave work on Silver Lake Rd. was postponed today due to rain, but will happen later this week.
Removal of existing/ installation of new aprons on Pecks Road begins Tuesday, Sept. 11 through Friday, Sept. 14. This work will also occur on Jason Street (Gale to Roselyn) and Tor Court starting Sept. 13 through Sept. 14.
During the work on Silver Road, there will be a single lane closure, with continued access to nearby businesses. No restriction on access to Pecks, Jason, and Tor Court.
Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.