These Pittsfield Streets Will Be Affected This Week
Please be advised of the following work that will take place June 28-July 2, as part of the City of Pittsfield’s 2021 Street Improvement Project.

Monday, June 28: pave-shim course on Arlington Street, Waverly Street, Velma Avenue
Tuesday, June 29: pave-shim course on Dalton Avenue & raise structures on Arlington Street
Wednesday, June 30: raise structures on Waverly Street & Cascade Street
Thursday, July 1: pave-shim course on Cascade Street & raise structures on Velma Avenue
Friday, July 2: continue to raise structures on Velma Avenue & final pave of Cascade Street
During this work, on-street parking is prohibited during the hours of 7 a.m. – 5 p.m. in these locations. Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.