Please note the following update to work scheduled for July 22-31, as part of the City of Pittsfield’s 2020 Street Improvement Project.
Wednesday, July 22- Friday, July 24: Removal and replacement aprons on John Street, Francis Avenue, Linden and Bradford streets.
Thursday, July 23-Friday, July 24: Milling shoulders for cold in place (pavement recycling process) on Elizabeth Street, Dawes Avenue, and Dorchester Avenue.
Monday, July 27 – Wednesday, July 29: Apron installation on Bradford Street, Madison Avenue, and Hollister Street.
Tuesday, July 28: Cold in place on Elizabeth Street.
Wednesday, July 29 – Thursday, July 30: Cold in place on Dorchester Avenue.
Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.