The following is from The Office of The Mayor...

Monday, July 16: milling and paving on Dalton Avenue, work around manhole covers begins on Henry Avenue and continues through Wednesday, July 18. Also, catch basin installation on Pecks Road begins and continues through Friday, July 20.

Tuesday, July 17: pave and shim Dalton Avenue.

Wednesday, July 18: milling on Henry Avenue.

Thursday, July 19: pave and shim Henry Avenue; curbing on Tor Court.

Friday, July 20: loam, seed, and cleanup Tor Court.

With the exception of Tor Court on Friday, July 20, on-street parking is prohibited during this time. Please note the schedule is subject to change based on weather conditions.

The City of Pittsfield thanks you for your patience during this time.